SWFWMD ERP* permits require that the stormwater system be inspected and certified every two years after the project has been transferred to operation and maintenance. Landmark Engineering & Surveying Corporation provides services to meet the SWFWMD inspection requirements by performing the following tasks:
1. Review the SWFWMD files and obtain copies of the as-built drawings for the stormwater management system
2. Conduct a field inspection of the stormwater management system to confirm it is operating in accordance with the approved as-builts and there have been no changes to the accepted stormwater management system
3. Prepare the required SWFWMD certification and submit for approval by SWFWMD
*SWFWMD ERP: Southwest Florida Water Management District, Environmental Resource Permit